High School Old Boys Club Rooms
Client
High School Old Boys Club
Location
Hagley Park, Christchurch
Duration
September - October 2022
Value
$260K
Role
Design Validation, Project Management & Site Investigations
Set within Christchurch’s most environmentally sensitive inner-city green space, this project called for more than just investigation work. LucasHaining was trusted to lead design validation, stakeholder coordination, and infrastructure investigations to support the development of new clubroom facilities—without disrupting park users, protected trees, or the seasonal touch rugby calendar.
LucasHaining was engaged directly by the High School Old Boys Rugby Club to manage design validation and lead horizontal infrastructure works supporting the new changing rooms within Hagley Park. With the site located in a highly protected environment surrounded by mature trees, waterways, and recreational use areas, delivery required careful planning, specialised methodology, and uncompromising environmental stewardship.
Our scope included utility service location, contamination testing (including coal tar), groundwater and subgrade investigations, and detailed tree root assessments to inform drainage design and final construction footprint. Early involvement allowed us to feed investigation data directly into the design process—preventing redesign delays and supporting accurate budgeting.
To protect the park and maintain public use, LucasHaining developed and implemented a comprehensive Environmental Management Plan (EMP), which was reviewed by CCC arborists, the Botanical Gardens team, and an independent environmental consultant. Each audit concluded with highly commended results.
We coordinated a trusted investigation team including:
Ben Maynard (KWC): survey and log sheet delivery
UINZ & JCL: hydro and air vac excavations
Road Tech Lab: IANZ-accredited ground profiling
SSL: reinstatement and surfacing
All works were completed on time and within budget—ensuring the critical drainage infrastructure was in place without delaying the upcoming sports season. Our proactive project management, strong technical delivery, and stakeholder-focused approach ensured that both the client and the wider CCC team could progress with confidence.