Naval Point Upgrades

Client
Christchurch City Council

Location
Naval Point, Lyttleton

Duration
February 2022 - April 2022

Role
Civil Programme Partner

With Christchurch securing SailGP, the upgrade of Naval Point was fast-tracked - and failure wasn’t an option. LucasHaining was engaged to help drive delivery across a complex, high-stakes site requiring methodical planning, smart coordination, and robust systems to support a fast-moving, stakeholder-heavy programme. 

The Naval Point Upgrade is a flagship project for Christchurch City Council, designed to transform Lyttelton’s waterfront into a world-class venue ahead of the international SailGP event. With significant community, political, and commercial interest, the project demanded precision, pace, and transparency.

LucasHaining was brought in for our reputation in delivering complex civil infrastructure under pressure. Leveraging our team’s deep understanding of local consenting pathways, construction methodologies, and the Canterbury contractor market, we were able to step into the programme and provide both delivery and strategic oversight.

Our scope included stormwater installation, concrete repair to key marine structures, underground and overhead service relocations, jetty demolition planning, and integration of streetscape and pavement upgrades. The site’s constraints - tidal cycles, marine interfaces, tight access, and overlapping stakeholder use - demanded rigorous coordination with groups such as the Coastguard, Lyttelton Port Company, local yacht clubs, and industrial tenants.

We implemented a robust suite of Inspection and Test Plans (ITPs) for each activity, outlining hold points, deliverables, and quality expectations - ensuring that each task was completed once, and completed right. The complexity of sequencing required our team to actively manage risk and adjust the programme without compromising quality or stakeholder needs.

Throughout the works, Scott Gebbie has provided CCC with ongoing, transparent cost reporting - allowing real-time tracking of dynamic scope changes and supporting agile, informed decision-making.

From enabling works to ongoing jetty preparation, LucasHaining’s role at Naval Point is a clear example of delivery leadership under pressure - helping CCC meet the moment for a globally watched event.