TeKaha Stadium External Works
Client
BESIX Watpac
Duration
2025
Value
$11.3M
Role
Project Management & Delivery Coordination
LucasHaining provided project management and delivery coordination for the $11.3 million external works package at Te Kaha, Christchurch’s new multi-use stadium.
The package comprised approximately 39,000m² of earthworks, 30,000m² of asphalt pavement, 2km of drainage, underground services, irrigation, landscaping and 10,400m² of turf.
Delivered alongside the wider stadium construction programme, the works required multiple specialist subcontractors to operate across tightly connected and continually changing work fronts. LucasHaining managed the construction programme, subcontractor coordination and interfaces between earthworks, drainage, services, pavement, irrigation and landscaping.
A key focus was looking ahead to identify upcoming constraints and ensuring each work front was ready for the next activity. Deliberate sequencing and progressive release of completed areas maintained momentum, reduced double handling and prevented following trades from compromising completed work.
The package was completed ahead of programme and on budget, with no non-conformances recorded.