TeKaha Stadium Field of Play

Client
BESIX Watpac

Duration
2025

Value
$4.7M

Role
Project Management
& Delivery Coordination

LucasHaining provided project management and delivery coordination for the specialist $4.7 million Field of Play package at Te Kaha.

The works comprised 10,660m² of earthworks, 4km of subsoil drainage, 410m of outfall drainage, 650m of irrigation, 4km of aeration infrastructure, engineered sand-carpet layers and 8,400m² of turf construction and establishment.

The Field of Play was constructed as an integrated performance system, where the quality, level and completion of each preceding layer directly influenced the performance of the finished playing surface.

LucasHaining coordinated multiple specialist contractors through the complete construction sequence, from earthworks and buried infrastructure through drainage, irrigation, aeration and engineered sand layers to final turf establishment.

With the Field of Play sitting within the wider stadium completion programme, protecting the turf establishment window was critical. LucasHaining programmed the works from the finished surface backwards, actively coordinating preceding work fronts and progressively releasing each layer before subsequent activities proceeded.

This approach-maintained programme momentum while providing clear quality control throughout the construction sequence and preventing latent defects from being carried into the finished field.

The Field of Play was completed ahead of programme and delivered ready for Christchurch City Council handover with zero defects.

Previous
Previous

Te Kaha Stadium External Work

Next
Next

Earlsbrook Stage 1